The latest images of construction at Hatta's new reservoir show it to be more than one third complete.

Officials released the photographs on Monday. They said the reservoir was 36.25 per cent of the way to completion and more than 4 per cent ahead of schedule.

It is being built by the Dubai Electricity and Water Authority (Dewa) at a cost of approximately Dh86 million ($23.4m). It will have capacity of about 30 million gallons of desalinated water and is expected to be completed by April of next year.